The Tennessee Department of Transportation contract crews will be closing the I-55 Mississippi River Bridge for two weeks to continue construction activities on the I-55 and Crump interchange
Emma Mason,
6 months ago
1 min read
Chattanooga, TN – According to the state officials, during the two-week closure, crews will hydro-demolition the bridge deck and provide a new polymer concrete overlay.
The polymer-modified concrete has strict temperature restrictions. All work is weather-dependent. The upcoming closure is the first of two allowed in the contract.
Sunday, June 9, 8:00 pm through Sunday, June 23, 8:00 pm
– I-55 SB will be closed at Bridgeport Road in Arkansas
– I-55 NB will be closed at South Parkway* in Tennessee
* Local traffic will be allowed to continue to the McLemore exit
– I-55 SB ramp will be closed
– Crump Boulevard WB will be closed
A detour will be posted.